ACC 561 Question 13-48, Overhead Variances

ACC 561 Question 13-48, Overhead Variances
Click to enlarge
Price: $5.00
Availability: In Stock
Model: A
Average Rating: 5 out of 5 Stars!

INSTANT DOWNLOAD

Solution Guide / Answer Key:

ACC 561
Axia College of University of Phoenix (UoP)
Introduction to Management Accounting
Horngren, C. T., Sundem, G. L., Stratton, W. O., Burgstahler, D., & Schatzberg, J. (2008). Introduction to Management Accounting (14th ed.). Upper Saddle River, New Jersey: Pearson-Prentice Hall.

3. Individual Assignment: Text Exercises

• Complete the following Problem Sets from the text. Show your work.

Question 13-48, Overhead Variances, on p. 622

13-48 Overhead Variances
Study Appendix 13. Consider the following data for the Rivera Company:
Factory Overhead
Fixed Variable
Actual incurred $14,200 $13,300
Budget for standard hours allowed
for output achieved 12,500 11,000
Applied 11,600 11,000
Budget for actual hours of input 12,500 11,400
From the above information, fill in the blanks below. Be sure to mark your variances F for favorable
and U for unfavorable.
a. Flexible-budget variance $______ Fixed $______ Variable $______
b. Production-volume variance $______ Fixed $______ Variable $______
c. Spending variance $______ Fixed $______ Variable $______
d. Efficiency variance $______ Fixed $______ Variable $______

 

FILE: MS EXCEL

Write Review
Your Name:


Your Review: Note: HTML is not translated!

Rating: Bad            Good

Enter the code in the box below:

There are no additional images for this product.