Exercise 18-5 (E18-5) Analysis of Percentage-of-Completion Financial Statements

Exercise 18-5 (E18-5) Analysis of Percentage-of-Completion Financial Statements
Click to enlarge
Price: $2.49
Availability: In Stock
Model: A
Average Rating: 5 out of 5 Stars!

INSTANT DOWNLOAD

Solution Guide / Answer Key:

ACCOUNTING

ACC 421
Intermediate Financial Accounting I
Axia College of University of Phoenix (UoP)

Intermediate Accounting
Weygandt, Kieso, Warfield

Week Three (Week 3)

Exercise 18-5 (E18-5) (Analysis of Percentage-of-Completion Financial Statements) In 2007, Beth Botsford Construction Corp. began construction work under a 3-year contract. The contract price was $1,000,000. Beth Botsford uses the percentage-of-completion method for financial accounting purposes. The income to be recognized each year is based on the proportion of cost incurred to total estimated costs for completing the contract. The financial statement presentations relating to this contract at December 31, 2007, follow.
Balance Sheet
Accounts receivable—construction contract billings $21,500
Construction in progress $65,000
Less: Contract billings 61,500
Cost of uncompleted contract in excess of billings 3,500
Income Statement
Income (before tax) on the contract recognized in 2007 $18,200
Instructions
(a) How much cash was collected in 2007 on this contract?
(b) What was the initial estimated total income before tax on this contract?

 